Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the change-wp-admin-login domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/u168781334/domains/cashmycurrency.com/public_html/wp-includes/functions.php on line 6260
Trans Mountain says ‘worst case’ could see pipeline project’s completion delayed to end of 2024 | Globalnews.ca – Cash My Currency- Financial Updates | Business Blog Post | Financial Guest Posting Services

Trans Mountain says ‘worst case’ could see pipeline project’s completion delayed to end of 2024 | Globalnews.ca

Trans Mountain says ‘worst case’ could see pipeline project’s completion delayed to end of 2024  | Globalnews.ca

The Crown corporation behind the Trans Mountain pipeline expansion says it may not complete the project before December 2024 if a regulator does not approve its request for a route deviation.

Trans Mountain Corp. says the new time frame is a worst-case scenario that could add close to $86 million in cost overruns to the final project price tag.

Trans Mountain Corp. had hoped to have the pipeline in service in early 2024 but has run into engineering difficulties related to the drilling of a tunnel in B.C.

It wants to alter the route slightly for a 1.3-kilometre stretch of pipe, as well as the construction method.

But it faces opposition from the Stk’emlupsemc te Secwepemc Nation, whose traditional territory the pipeline crosses and who had agreed to the originally proposed route and construction method.

Story continues below advertisement

The Canada Energy Regulator will hear arguments from both Trans Mountain and the First Nation at a hearing in Calgary next week.

&copy 2023 The Canadian Press